Monday, November 5, 2012


 
Pics 1 and 2 show some of the landscaping that's been done.  Some of the river rocks have been re-used.

 

 shows the counter electrodes installed.
 shows the beginning of the buss bars being installed.
 show the blower motor mounted and bolted down.
 shows the water softener in place with some plumbing started to the right and above.
 
shows work being done on the ADA path of travel.  Overhead space is tight but work seems to be going good.

 

shows drywall work being completed at the south roll up door.

Notes:

 

*Electricians are almost done with contract work and have started some T&M.

*Plumbers are going to town on piping.

*The stairs to the catwalks are now installed but not painted.

*The grating has been temporarily installed on the north-south catwalk to provide better access.

*The rims on the CO-PP liners is being worked on and 4 are completed.

*The stainless steel welding for the beams is coming along nicely being done by Tom Enos.

*Most of the buss bars have been beveled in preparation for installation this weekend.

*The ongoing plague with the security system may have been corrected today, time will tell.  Cal Safety placed another code pad in the main electrical room downstairs at no charge to help.

*Installation of the cable carrier and hopefully the cable will happen Saturday.  Electricians will provide the electrical connections to the control panel early next week.

*Installation of the dryer motor is planned for installation early next week if it can't be done this weekend.  Wiring of the control panel will be early next week.