Pics 1 and 2 show some of the landscaping that's been
done. Some of the river rocks have been
re-used.
shows the counter electrodes installed.
shows the beginning of the buss bars being installed.
show the blower motor mounted and bolted down.
shows the water softener in place with some plumbing started to the right and above.
shows work being done on the ADA path of travel. Overhead space is tight but work seems to be
going good.
shows drywall work being completed at the south roll up door.
Notes:
*Electricians are almost done with contract work and have
started some T&M.
*Plumbers are going to town on piping.
*The stairs to the catwalks are now installed but not
painted.
*The grating has been temporarily installed on the
north-south catwalk to provide better access.
*The rims on the CO-PP liners is being worked on and 4
are completed.
*The stainless steel welding for the beams is coming
along nicely being done by Tom Enos.
*Most of the buss bars have been beveled in preparation
for installation this weekend.
*The ongoing plague with the security system may have been
corrected today, time will tell. Cal
Safety placed another code pad in the main electrical room downstairs at no
charge to help.
*Installation of the cable carrier and hopefully the
cable will happen Saturday. Electricians
will provide the electrical connections to the control panel early next week.
*Installation of the dryer motor is planned for
installation early next week if it can't be done this weekend. Wiring of the control panel will be early
next week.