Tuesday, November 13, 2012

 
15 shows the entire west wall painted floor to ceiling, and the south wall half done.

 
Pic 16 shows landscape work being done adjacent to Caterpillar Rd.

 

 
Pic 17 shows new parts to be used for the RPP/fire hydrant being installed at Beltline Road.
Note that there will likely need to be a fire watch while the thrust blocks sit for 24 hours, which may be tomorrow or Thursday.

 
Pic 18 shows the beginning of excavation at Beltline Road.  The PVC line in the background may be the irrigation line for Beltline Road, TBD by T&M work.

 
Pic 19 shows the hoist with power hooked up to it from the cable carrier.  The End of Line J box is also installed with wiring to it from conductors leading to the control panel which also has the wiring landed.  Wiring from the cable carrier to the J box is the only item left and we're waiting on Jessup to give direction as to how the cable carrier terminates at the elevated trough.


Pic 20 shows the mounting panels that will be used for the 2 step and anodizing controls as well as Shasta Controls main panel.  This is also set up for any future controls for 2 step and anodizing.