Signage 1
Signage 2
Placarding on building
labeling on process piping 1
Labeling on process piping 2
Labeling on process piping 3
shower stands
shower stand at storage area
rectifier controls
bus bars in anodizing tanks 1
bus bars in anodizing tanks 2
bus bars in anodizing tanks 3
cathode
dryer (it is running)
boiler in operation 1
boiler in operation
cooling tower
new roll up doors 1
new roll up doors 2
new roll up doors 3
tank anchorage 1
tank anchorage 2
Friday, November 30, 2012
Wednesday, November 28, 2012
Friday, November 16, 2012
shows the circuit setters were installed today but the
return piping to the chiller hasn't been connected.
1 shows the unistrut frame installed and a steam piping
assembly attached for the seal tank.
There's also similar assembly steam piping for the fluoride and caustic
tanks already made and should be installed tomorrow (I hope).
2 shows the poly heat exchangers at both ends of the
fluoride tank.
The mounting at the top of both heat exchangers had to be
completely modified to fit over the CO-PP liners which worked out for the
better because they are now both stronger and easier to remove if needed.
shows a lot of material moved to be able to
accept the 20' brake tomorrow.
shows the roll up door at the loading dock installed. The roll up between Absolute and anodizing is also in, but not the one between the north warehouse and anodizing.
shows the roll up door at the loading dock installed. The roll up between Absolute and anodizing is also in, but not the one between the north warehouse and anodizing.
1 shows the fire extinguisher in with the paving done
over the top.
The pipe terminates near Beltline Road at the open pit.
shows the open pit and the blue pipe to the right is the
one that will feed the fire extinguisher.
This work isn't supposed to start back up until Tuesday of next week,
the reason is waiting on parts is what I was told. It's likely to rain so they might have a
swimming pool after the weekend.
shows the cover over the flume. The railroad ties were left overs that were
used to help support the trench plates in the wide gaps. The flume is set in sand and dirt, no concrete. The railroad ties and cover help provide
weight to help prevent the flume from wanting to float.
Tuesday, November 13, 2012
15 shows the
entire west wall painted floor to ceiling, and the south wall half done.
Pic 16
shows landscape work being done adjacent to Caterpillar Rd.
Pic 17 shows
new parts to be used for the RPP/fire hydrant being installed at Beltline Road.
Note that
there will likely need to be a fire watch while the thrust blocks sit for 24
hours, which may be tomorrow or Thursday.
Pic 18 shows
the beginning of excavation at Beltline Road.
The PVC line in the background may be the irrigation line for Beltline
Road, TBD by T&M work.
Pic 19 shows
the hoist with power hooked up to it from the cable carrier. The End of Line J box is also installed with
wiring to it from conductors leading to the control panel which also has the
wiring landed. Wiring from the cable
carrier to the J box is the only item left and we're waiting on Jessup to give
direction as to how the cable carrier terminates at the elevated trough.
Pic 20 shows
the mounting panels that will be used for the 2 step and anodizing controls as
well as Shasta Controls main panel. This
is also set up for any future controls for 2 step and anodizing.
Pic 1 shows the south roll up door area ready for
paint. Roll up doors were supposed to be
installed this last week but they're apparently waiting on this work to be
complete.
Pic 2 shows the work at the 4300 building Path of
Travel. The same access mat used prior
to the exterior door will also be used in the vestibule to avoid multiple
colors contrasting into the building.
This mat appears to be very durable and apparently priced well. Demolition has stopped and as you can see the
back fill has been installed and compacted.
Pic 3 shows the electrical completed at the
concentrate storage area.
The plumbing for these are mostly complete
also however the final tie ins to the tanks inside the building have not been
met yet. The last caustic tank will be
removed to allow for installation of the eye wash/shower/holding tank.
Pic 4 shows all of the splash walls installed. In the background you can also see that the
handrail on top of the Crystallizer has also been installed. The steam ports on the side of the
Crystallizer have also been removed and welded shut. If zoomed in, you can see that the caustic
and sulfuric plumbing has been installed up to the DMP holing tanks, but the
bulkhead fittings haven't been installed yet.
Pic5 shows the
electrical hooked up to all of the rectifiers.
This ended up being contract work where it was thought to be T&M.
Some motor hook ups are also contract work.
Notice in the background the buss bars welded up through the verticals
near the tanks (first anodize tank only so far).
Pic 6 shows the cable
carrier and cable pulled so that it can be hooked up to the control panel next
week when the electricians are done with contract work (likely Wednesday). Wiring will be hooked up to the hoist and
down to the End of Line J box today.
Pic7shows the 2"
x 6" buss bars being cut to length after being welded together. These are for ano tank 1.
.

Pics 11 and 12 show the path of travel work done up to the 4300 building
Pics 13 and 14 show
the work done at the path of travel today.
Notes
*Sunrise began
excavation of the new fire hydrant today.
They broke a small copper line underground but were able to shut water
off to it. At the time they didn't know
what it went to. I understand that they
will have to have a watch person all night since the trench will be open and
there needs to be a fire watch.
*Mounting panels were
installed so that the 2 step and anodizing controls can be mounted. Shasta Controls will use the same mounting
panels which are scrap aluminum sheet attached to unistrut between the vertical
hoist posts.
Subscribe to:
Posts (Atom)