The new fence with gates to the terrace/north warehouse and to the concentrated storage area. Lasers following the fence line to be installed early next week by Cal Safety.
Cone tanks are located and the perimeter splash wall is substantially completed.
*Electricians have worked several weekends, drywall crew worked this weekend also.
*Emergency generator set and anchored today. Wiring for it has also begun.
*Plans to install the hoist onto the hoist framework are made.
*Having the starter for the breaker for the CO-PP welding compressor replaced, went out on night shift last night.
*Soaker hoses have been placed at the bushes west of the SAF/County offices as a temporary irrigation method. Same for Caterpillar Rd prior to the driveway.
*Looking into renting trench plates for installing process tanks. The weight of tanks and lift are significant for the spans so blocking devices are being considered as well.
*Work on the hoist structure has been quiet the latter part of this week. The construction Superintendent is to update their plans for moving forward.
*ADA access will be by re-pouring the concrete. Mud jacking is not a good alternative with so many expansion joints.