Tuesday, October 9, 2012

shows the Chemineer agitator installed with shafts and propellers on the Crystallizer tank. We used a jib on a forklift to hold the motor while attaching the shaft. We're now ready to have the handrail installed above, then foam and paint the outside of the tank. Many of the floor grates are installed making access much easier. The hoist structure is fully painted and the white paint is great for reflecting the lighting.


shows some of the catwalk parts pre-painted while other parts are coming in with red oxide primer coating. We don't have a firm date for catwalk installation yet.

shows manifolds coming off the chiller. Core drilled holes are in the new locations outside to the cooling tower.
shows the cooling tower and generator, but no plumbing appears to have been done yet for the cooling tower.
*The catwalk anchor lay out is being done today preparing for special inspection of setting the ahchors.
*Overhead steam piping is being installed today and tomorrow morning prior to the catwalk being installed.
*Electricians are almost done with contract work.