shows the hoist on the frame and the catwalk handrails in place.
The handrails and catwalk are to be painted today, so tanks east of the north-south catwalk will be placed tomorrow or Thursday.
shows painting done on the north wall.


shows painting done on the catwalk.
shows the roll up door framework and sheet rock being installed at the north warehouse.

*110v and welding plugs are being installed on west and south walls.
*Steam pipes are installed and being pressure tested.