shows the beginning of the catwalk installation. Trench plates should be coming by the end of this week/beginning of next week which will likely be used by the plumbers for overhead work to save us on the "T" of T&M.
shows the caustic concentrate tanks now insulated. The heaters are in them and the pumps are to be installed tomorrow. The tanks will also be set in their permanent locations, fill pipes will be ran, and controls set on the exterior of the east wall of the boiler room. NOTE the scrubber exhaust above the roof line.