T-bar dropped ceiling being installed in the break room.
The walls have already been painted and the HVAC work has been done.
Lights have already been installed.
shows the bathrooms adjacent to the anodizing break room. The toilets, sinks and flooring is installed. The lights are being worked on.
The hoist framework being painted and it really brightens up the already painted areas. Should be done by Thursday 10/4/12. The drywall is installed on all of the anodizing side and 70% of north warehouse side. Still needs to be taped, textured and painted.
2 crews are welding the CO-PP tank liners as of this week.
chiller after being moved about 7' to the east.
view from the south-east part of the anodizing area. The splash wall is designed to give some life to the area making a more vibrant working environment, and because this exposed side is the reverse side of coil anodized scrap aluminum sheet, it reflects light better and we were able to salvage unsaleable sheet. All interior drywall will have been hung after this section is done today. All air socks have been hung. The DMP system was inspected yesterday and the inspector seemed satisfied with our operation.