Thursday, August 30, 2012




Pic 1: Most posts and 6 horizontal I-beams are installed with welded east/west bracing. This is a tough install but it's going smoothly.
Pic 2: Plumbing install for water service as of 3:30 p.m. Thursday in TORR1. Welding time of this material seems very inefficient @ 1/2 hour per coupling.
Pic 3: Process tank liner #1 is finished. Estimated time of completion of 16 total is the end of October with one shift, but we'll likely have
2 shifts working to cut this time in 1/2.
Pic 4: Electrical panel install on the south side of anodizing line.
Notes:
*All infill panels are paint ready in the TORR spaces.
*Bathroom drywall hung at the anodizing space.
*OES working on the ventilation work.