Other notes:
*New main power cabinets are installed but not approved by the City yet. Still dark in most places.
*The concrete contractor expects to be done by late next week.
*Removal of the air handler and other misc work has started in the welding area.
*Gas lines have been installed through the building, PGE to begin their underground work next week.
*Wall framing has been installed on the south wall of the north warehouse for fire barriers.
*TORR bathrooms are painted and the linoleum floors are in. Doors are being installed today.
*The TORR space to be complete by Wednesday 8/15/12 with the exception of the roll up door which has been delayed 1-2 weeks.
*The common hallway and TORR spaces are being re-keyed. The "common entry" is being made ADA and Fire compliant.
*California Safety is altering the security system to accommodate the common hallway and TORR spaces.