Thursday, August 16, 2012




Pic 1: Most interior concrete work is done.
Pic 2: The rough work in the weld room is complete. Finish and clean up to follow. Note the pre-existing crane framework.
Pic 3: The footing trench for the wall at the caustic/sulfuric holding tank area is dug.
Pic 4: Exterior concrete forms for the chiller and generator are being prepared.
Notes:
* PG&E has just installed the new gas lines to Caterpillar Rd.
* The trench is dug and electrical conduit is being placed for power to the sign monument west of the driveway.
* Concrete pouring is scheduled to be complete by this Monday 8/20/12, cleanup to last a few days extra.
* SAF's clean-out of the boiler basement has begun.
* Work for the security systems and door accesses to the community hallway have been set in motion, not complete.
* TORR space is finished less the roll up fire door. Water is on including water fountains.