Friday, August 24, 2012



Pic 1: Ducting being installed over the anodizing pit.
Pic 2: Firewall being installed at the south-west corner of the anodizing area.
Pic 3: Concrete for the chiller and generator completed.
Notes:
*All concrete is done except the partition wall near the caustic/sulfuric concentrate storage and at the trough location north of the anodize pit.
*The TORR space final is complete, TORR to move in Sept. 1st. Very minor work being finished up there.
*Murray Plumbing is installing the water service through the TORR space prior to their occupation.
*CO-PP is on site as of today. Waiting for power for welder and compressor to be installed, likely tomorrow.
*Scrubber is on site, interestingly it's made of PVC. Will be installed during the hoist frame erection.
*Prior electrical vandalism of the 4300 building to start, estimated time frame 1 to 1.5 weeks.
*Work in the weld shop is complete except for the welder outlet to be installed.
*Hoist frame to begin installation Monday 8/27/12.
*T&M work to fireproof the vertical posts on the north side of the anodizing pit approved. This work wont start until the hoist frame is installed.
*Process tanks approved for installation, but can't happen until after the hoist frame is installed.