Pic 1: Water tank was moved inside the building with no problems.
Pic 2: Process tank #2 is complete and getting painted, to be delivered tomorrow 6/1/12.
Pic 3: Process tank #1 passes the water proofing with no problems.
Pic 4: 2 hour fire proofing of separation wall has begun.
Notes: Overhead fire sprinkler work is complete. Overhead conduit still being put in; waiting on fixtures before excavation can begin.dave