Pic 2 shows tank forms being installed for the Crystallizer and Clarifier tanks.
Pic 3 shows the roof/cricket area being worked on.
Pic 4 shows the new door installed at the community hallway near the TORR office.
Pic 5 shows sand being delivered for the concrete base in the anodizing pit.
Notes:
*Holes are being drilled in the concrete at the anodizing pit to be able to add rebar to tie into the new concrete when poured.
*480v electrical is being brought to the existing SAF fabrication area.
Panels are in and wires are being pulled.
*The drywall firewall between the trapezoidal room and SAF fabrication is mostly installed but not complete. Cerami waiting on RFI for procedure around fire sprinkler pipe.
*15 of 20 process tanks are completed and painted.
*TORR bathrooms are ready for texture and paint.
*The door to the 4300 building in the community hallway is installed and drywalled, ready for texture and paint.
*The electrical panels for the TORR space are installed.