Wednesday, July 25, 2012
Pic 1: Rebar being installed in the anodizing pit.
Pic 2: Forms for tanks installed.
Pic 3: All misc. framing done including bathrooms.
Notes:
*Concrete scheduled to be poured Monday 7/30.
*6" fire pipe problem resolved between trapezoidal room and SAF production to allow fire wall to be installed.
*TORR swamp coolers have arrived and openings in roof being worked on.
*16 process tanks complete and 17 in the works.
*Crystallizer tank work beginning.
*Fence at Caterpillar Rd being removed currently. Part of this scope includes the guard shack to be demo'd, and a business monument to be installed.
*Lots of landscape work being done.