Wednesday, July 25, 2012



Pic 1: Rebar being installed in the anodizing pit.
Pic 2: Forms for tanks installed.
Pic 3: All misc. framing done including bathrooms.

Notes:
*Concrete scheduled to be poured Monday 7/30.
*6" fire pipe problem resolved between trapezoidal room and SAF production to allow fire wall to be installed.
*TORR swamp coolers have arrived and openings in roof being worked on.
*16 process tanks complete and 17 in the works.
*Crystallizer tank work beginning.
*Fence at Caterpillar Rd being removed currently. Part of this scope includes the guard shack to be demo'd, and a business monument to be installed.
*Lots of landscape work being done.

Monday, July 23, 2012






Pic 1 shows excavation and compaction of the anodizing pit.
Pic 2 shows tank forms being installed for the Crystallizer and Clarifier tanks.
Pic 3 shows the roof/cricket area being worked on.
Pic 4 shows the new door installed at the community hallway near the TORR office.
Pic 5 shows sand being delivered for the concrete base in the anodizing pit.


Notes:
*Holes are being drilled in the concrete at the anodizing pit to be able to add rebar to tie into the new concrete when poured.
*480v electrical is being brought to the existing SAF fabrication area.
Panels are in and wires are being pulled.
*The drywall firewall between the trapezoidal room and SAF fabrication is mostly installed but not complete. Cerami waiting on RFI for procedure around fire sprinkler pipe.
*15 of 20 process tanks are completed and painted.
*TORR bathrooms are ready for texture and paint.
*The door to the 4300 building in the community hallway is installed and drywalled, ready for texture and paint.
*The electrical panels for the TORR space are installed.

Thursday, July 5, 2012



Pic 1: The 4 electrical conduits that were too high under the slab have had the conductors removed and are in process of being lowered. Several sewer pipes were found which are being capped off and aren't needed per demolition plans.
Pic 2: TORR bathroom work still moving forward.
Pic 3: 4300 building electrical panel installed and powered up. The door framing @ the community hallway and other openings at the TORR space framed in.
Other notes: Excavation should begin next week.

Monday, July 2, 2012


*MCC panels for SAF and TORR are in although switch gear isn't.
*Plumbing trenches are being back filled in the anodizing area.