Thursday, September 6, 2012
Pic 1: Handicap path to Caterpillar Rd. started.
Pic 2: Crystallizer tank almost complete. About 1 week behind schedule but looking good. Top section (background) to be mounted today. All parts are made, assembly only.
Pic 3: Power panels and OES work being installed.
Pic 4: Assembly of hoist framework coming along. Still lots to do.
Notes:
*Starting the 3rd tank liner. To begin a night shift starting tomorrow
9/7/12 welding liners.
*TORR moved in but still waiting for high voltage install.
*Large waste water tank to be installed tomorrow, anchor holes drilled a 2nd time for seismic anchors.
*Working on splash guards for the waste water tank and the waste water containment area.
*Some T&M work began for plumbers.
All the best,
dave