Pic 1: Anodizing area with concrete removed, some plumbing in.
Pic 2: Middle basement area almost cleaned out.
Pic 3: TORR exterior and interior rough plumbing in.
Notes:
*Norris Steel has begun working on the 10th process tank.
*The anodizing bathroom plumbing excavation is done.
*Firewall between SAF and the adjacent north "trapezoid room" is started.
*The roof is removed and partially framed at the anodizing room's south roll up door.
Pic 1: More overhead ducting and electrical conduits are being installed.
Pic 2: Some new lighting is installed, and the light produced is great.
Pic 3: Concrete cutting has begun preparing for excavation in both the anodizing area and TORR lease space.
Pic 4: Concrete forms have arrived.
Pic 1: Anodizing bathrooms in the remodel process by Cerami Construction.
Pic 2: Excavation of the anodizing containment area has begun!
Pic 3: 6 anodizing tanks are completed by Norris Steel.