Friday, March 30, 2012




Majority of recyclable materials removed including ducts, piping, conduit, ceiling tiles and frame work. The interior northern wall is being prepared for removal and replaced with fire rated material. Some light fixtures have been elevated to be used for temporary lighting.

Sunrise Excavating believes that the major demolition will begin early next week using an excavator and/or backhoe. (comments by djs)

Friday, March 23, 2012



Week 2 of remodel. Ceiling tiles have been removed and some wall sections have been knocked down. The first load was hauled off this week.