20 Foot brake press in use. (New 20’ punch and dies were
delivered after these photos were taken)
Friday, November 30, 2012
Signage 1
Signage 2
Placarding on building
labeling on process piping 1
Labeling on process piping 2
Labeling on process piping 3
shower stands
shower stand at storage area
rectifier controls
bus bars in anodizing tanks 1
bus bars in anodizing tanks 2
bus bars in anodizing tanks 3
cathode
dryer (it is running)
boiler in operation 1
boiler in operation
cooling tower
new roll up doors 1
new roll up doors 2
new roll up doors 3
tank anchorage 1
tank anchorage 2
Signage 2
Placarding on building
labeling on process piping 1
Labeling on process piping 2
Labeling on process piping 3
shower stands
shower stand at storage area
rectifier controls
bus bars in anodizing tanks 1
bus bars in anodizing tanks 2
bus bars in anodizing tanks 3
cathode
dryer (it is running)
boiler in operation 1
boiler in operation
cooling tower
new roll up doors 1
new roll up doors 2
new roll up doors 3
tank anchorage 1
tank anchorage 2
Wednesday, November 28, 2012
Friday, November 16, 2012
shows the circuit setters were installed today but the
return piping to the chiller hasn't been connected.
1 shows the unistrut frame installed and a steam piping
assembly attached for the seal tank.
There's also similar assembly steam piping for the fluoride and caustic
tanks already made and should be installed tomorrow (I hope).
2 shows the poly heat exchangers at both ends of the
fluoride tank.
The mounting at the top of both heat exchangers had to be
completely modified to fit over the CO-PP liners which worked out for the
better because they are now both stronger and easier to remove if needed.
Subscribe to:
Posts (Atom)