Thursday, December 27, 2012

 
20 Foot brake press in use. (New 20’ punch and dies were delivered after these photos were taken)








New cantilever racks being installed.



Photos of SAF WEST anodizing extrusions. I apologize for the long laps between photos.











Friday, November 30, 2012

 Signage 1
 Signage 2
 Placarding on building
 labeling on process piping 1
 Labeling on process piping 2
 Labeling on process piping 3
 shower stands
 shower stand at storage area
 rectifier controls
 bus bars in anodizing tanks 1
 bus bars in anodizing tanks 2
 bus bars in anodizing tanks 3
 cathode
 dryer (it is running)
 boiler in operation 1
 boiler in operation
 cooling tower
 new roll up doors 1
 new roll up doors 2
 new roll up doors 3
 tank anchorage 1
tank anchorage 2

Wednesday, November 28, 2012

 
Working being done for safety shower at caustic holding tanks.

 
Concrete drying above underground storage tank for safety shower drainage.

 
Univar chemical being delivered for process tanks.

 
New RPP being installed.

New fire hydrant

Friday, November 16, 2012

shows the circuit setters were installed today but the return piping to the chiller hasn't been connected.
 

 
1 shows the unistrut frame installed and a steam piping assembly attached for the seal tank.  There's also similar assembly steam piping for the fluoride and caustic tanks already made and should be installed tomorrow (I hope).



2 shows the poly heat exchangers at both ends of the fluoride tank. 

The mounting at the top of both heat exchangers had to be completely modified to fit over the CO-PP liners which worked out for the better because they are now both stronger and easier to remove if needed.